Application of Arturo PU7320 Sealer

Prior to application:

Prior to the processing the Arturo PU7320 Sealer the following points are important:

  • Arturo PU7320 Sealer should always be applied in two layers. The application of the second layer may min. 16 hours and max. 24 hours be performed after the application of the first layer.
  • Check the conditions in space (temperature / humidity / dew point)
  • Take precautions for safe handling of the product

Processing step-by-step

1. Packaging containing B-component and sieve

1. Packaging containing B-component and sieve

2. Pour the B-component in the A-component in the bucket.

2. Pour the B-component in the A-component in the bucket.

3. Mix the A and B component at least two minutes.

3. Mix the A and B component at least two minutes.

4. Pour the mixed sealer in a clean bucket through the sieve. Wait 10 minutes before processing.

4. Pour the mixed sealer in a clean bucket through the sieve. Wait 10 minutes before processing.

5. Apply the sealer along the floor edges with a brush.

5. Apply the sealer along the floor edges with a brush.

6. Then roll the edges with a nylon roller (10cm). Do not work too much ahead.

6. Then roll the edges with a nylon roller (10cm). Do not work too much ahead.

7. Subsequently apply the sealer using a completely moistened roller 25cm (14mm pile height). Divide the sealer very evenly by rolling crosswise min. twice in the same direction.

7. Subsequently apply the sealer using a completely moistened roller 25cm (14mm pile height). Divide the sealer very evenly by rolling crosswise min. twice in the same direction.

8. Within 10 minutes after applying, roll with a slightly damp nylon roller 50cm (14 mm pile height) the topcoat on Cleat in one run transverse to the applied layer.

8. Within 10 minutes after applying, roll with a slightly damp nylon roller 50cm (14 mm pile height) the topcoat on Cleat in one run transverse to the applied layer.